A central AC change-out replaces the outdoor condenser and, in a proper job, the indoor coil with it. The labor is refrigerant work that only certified technicians may do. Reno's flat permit for an A/C change out is $45.00; Grand Rapids charges $21.00 for replacement equipment on top of a $52.00 application. HVAC mechanics earn a national median of $29.33 an hour.

Condenser only is a false economy

The outdoor unit and the indoor coil are designed as a pair. Bids that replace only the condenser look cheaper and often are not allowed by the manufacturer's rating for the new unit. If the refrigerant type has changed since the old system went in, the coil has to go too. Ask every bidder whether the price is a matched system and get the coil model number in writing.

What takes the time

Recovering the old refrigerant comes first. Under Section 608 of the Clean Air Act it cannot be vented, and the people handling it must be certified. Then the old equipment comes out, the pad is leveled or replaced, the coil is fitted to the furnace or air handler, and the line set is either flushed and reused or replaced.

The line set is the swing item. If it runs through an open basement, replacing it is easy and worth doing. If it is buried in a finished wall, replacement means opening the wall or rerouting outside. Reuse is common and can be fine; the bid should say which.

After that: brazing, a pressure test, pulling a deep vacuum, charging, and checking the numbers under load. The vacuum cannot be rushed. A crew that is in and out in no time did not do it.

Electrical odds and ends

A new condenser may need a different breaker size, a new disconnect or a new whip. These are small, but they are electrician's work in many jurisdictions and they carry their own permit line. Grand Rapids, for instance, lists A/C under its electrical fees as well as its mechanical ones.

HVAC mechanics, United States, May 2025 wages. Loaded cost adds 43.8% for benefits and required employer costs. The implied columns divide loaded cost by one minus a gross margin. Arithmetic on public averages, not a quote. For your own metro, open the HVAC mechanic pages.
National wage pointWage / hrLoaded / hrImplied billed hr, 15.5% marginImplied billed hr, 29.9% marginOne worker-day (8 hr) at 29.9%
25th percentile$23.25$33.44$39.56$47.71$382
Median$29.33$42.19$49.90$60.18$481
75th percentile$37.05$53.29$63.04$76.02$608

See HVAC mechanic wages for every metro.

Electricians, United States, May 2025 wages. Loaded cost adds 43.8% for benefits and required employer costs. The implied columns divide loaded cost by one minus a gross margin. Arithmetic on public averages, not a quote. For your own metro, open the electrician pages.
National wage pointWage / hrLoaded / hrImplied billed hr, 15.5% marginImplied billed hr, 29.9% marginOne worker-day (8 hr) at 29.9%
25th percentile$23.76$34.18$40.43$48.75$390
Median$30.38$43.70$51.69$62.34$499
75th percentile$40.36$58.05$68.67$82.82$663

See electrician wages for every metro.

Permit lines

Permit fee lines read from each city's published schedule in November 2026. Lines stack: an application or minimum fee usually sits under the item fee, and plan review, state surcharges and re-inspections come on top. Check your own city.
CityLine on the scheduleFeeSchedule
Reno, NVResidential EZ permit: A/C change out$45.00EZ Permits and Miscellaneous Fees, effective July 1, 2026
Portland, OROne and two family dwelling mechanical permit, minimum fee$167.00Mechanical Permit Fee Schedule, effective July 10, 2026
Portland, ORAir conditioning (site plan required)$44.00Mechanical Permit Fee Schedule, effective July 10, 2026
Grand Rapids, MIMechanical permit application, includes 1 inspection$52.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
Grand Rapids, MIMechanical, residential replacement: air conditioning unit or heat pump$21.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
Grand Rapids, MIElectrical permit application, includes 1 inspection$52.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
Grand Rapids, MIElectrical: A/C$10.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026

Portland's schedule marks its air conditioning line "site plan required", so expect to show where the outdoor unit will sit.

Equipment price trend

Producer prices for air conditioning and refrigeration equipment are 62.1% higher than in January 2020 and 4.1% higher than a year ago.

Producer prices for the main materials on this job. Latest index level for each series, with the change over 12 months and since January 2020. Each row uses the latest month that has a year-earlier reading. (p) marks a preliminary PPI figure; BLS revises indexes for up to four months after first publication. Source: BLS.
SeriesBLS series IDMonthIndex12 monthsSince Jan 2020
Air conditioning and refrigeration equipmentWPU1148October 2026 (p)325.9+4.1%+62.1%
CPI-U, all items, U.S. city averageCUUR0000SA0September 2026336.9+3.7%+30.6%

Comparing bids

Model numbers for both halves. Line set: new or reused. Refrigerant type. Thermostat included or not. Permit and electrical included or not. Labor warranty in years. Then compare totals.

Can I get the old federal tax credit for a new AC?

Not for work done now. The IRS says the Energy Efficient Home Improvement Credit covered improvements made through December 31, 2025.

Why is there an electrical permit on an AC quote?

Because the condenser's circuit, disconnect or breaker is being altered. On Grand Rapids's schedule that is a $52.00 application plus a $10.00 A/C line, separate from the mechanical permit.