Rewiring a house: the cost is in the walls

Rewiring an occupied, finished house is one of the most labor-heavy electrical jobs there is, because the wire is cheap and the route to pull it is not. Portland permits it by floor area: $408.00 for the first 1,000 square feet, service included, and $93.00 per additional 500. Electricians earn a national median of $30.38 an hour, about $499 per implied worker-day at a remodeler's margin.

Open walls or closed walls

That is the question that decides everything. In a gutted house an electrician drills studs and pulls cable through open framing at speed. In a finished house every run is fished: down from the attic or up from the basement, through holes cut at the top and bottom of each wall cavity, around fire blocks nobody knew were there. The same circuit takes several times the labor.

If you are planning other work that opens walls, such as a kitchen or a repipe, rewire then. The saving is larger than any negotiating you can do on rate.

What a full rewire includes

What it often does not include: patching and painting the access holes. As with a repipe, find out who closes the walls.

Estimating the labor

Electricians bid rewires from a count: rooms, openings (each outlet, switch and light is one), stories, and whether there is an attic and basement to work from. Lath and plaster is slower than drywall. Finished basements and flat roofs take away the easy routes.

Electricians, United States, May 2025 wages. Loaded cost adds 43.8% for benefits and required employer costs. The implied columns divide loaded cost by one minus a gross margin. Arithmetic on public averages, not a quote. For your own metro, open the electrician pages.
National wage pointWage / hrLoaded / hrImplied billed hr, 15.5% marginImplied billed hr, 29.9% marginOne worker-day (8 hr) at 29.9%
25th percentile$23.76$34.18$40.43$48.75$390
Median$30.38$43.70$51.69$62.34$499
75th percentile$40.36$58.05$68.67$82.82$663

See electrician wages for every metro.

Drywall installers, United States, May 2025 wages. Loaded cost adds 43.8% for benefits and required employer costs. The implied columns divide loaded cost by one minus a gross margin. Arithmetic on public averages, not a quote. For your own metro, open the drywall installer pages.
National wage pointWage / hrLoaded / hrImplied billed hr, 15.5% marginImplied billed hr, 29.9% marginOne worker-day (8 hr) at 29.9%
25th percentile$22.81$32.81$38.81$46.80$374
Median$28.33$40.75$48.20$58.13$465
75th percentile$35.69$51.34$60.73$73.23$586

See drywall installer wages for every metro.

Ask each bidder for crew size and duration and multiply. This is a job where the worker-days are large enough that the 25th and 75th percentile rows are far apart in dollars. Who is on the crew matters.

Permit lines

Permit fee lines read from each city's published schedule in November 2026. Lines stack: an application or minimum fee usually sits under the item fee, and plan review, state surcharges and re-inspections come on top. Check your own city.
CityLine on the scheduleFeeSchedule
Portland, ORResidential wiring package, new and remodels, 1,000 square feet or less, service included$408.00Electrical Permit Fee Schedule, effective July 10, 2026
Portland, ORWiring package, each additional 500 square feet or portion$93.00Electrical Permit Fee Schedule, effective July 10, 2026
Grand Rapids, MIElectrical permit application, includes 1 inspection$52.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
Grand Rapids, MIElectrical: general branch circuit$10.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
Grand Rapids, MIElectrical: up to 200 amp service$17.00Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026

Portland's wiring package fee is the clearest published example of how cities scale a rewire permit to house size. Grand Rapids builds the fee from an application plus per-circuit and service items.

Copper and devices

Producer prices for the main materials on this job. Latest index level for each series, with the change over 12 months and since January 2020. Each row uses the latest month that has a year-earlier reading. (p) marks a preliminary PPI figure; BLS revises indexes for up to four months after first publication. Source: BLS.
SeriesBLS series IDMonthIndex12 monthsSince Jan 2020
Copper wire and cableWPU10260314October 2026 (p)610.0+25.5%+101.9%
Wiring devicesWPU1171October 2026 (p)397.6+4.8%+66.1%
CPI-U, all items, U.S. city averageCUUR0000SA0September 2026336.9+3.7%+30.6%

Comparing bids

Get the opening count on each bid. Confirm arc-fault and ground-fault protection are included where required, that the smoke alarms are in, that the panel scope is stated, and that there is a price per additional opening for the things you will think of later. Ask how they protect floors and how many holes to expect per room.

Is copper the reason rewires are expensive?

No. Copper wire and cable is 101.9% higher at the producer level than in January 2020, but cable is still a minor share next to many worker-days of electrician labor at a loaded cost near $43.70 an hour.

How is a rewire permit priced?

Portland uses a wiring package by floor area: $408.00 for 1,000 square feet or less including the service, then $93.00 for each further 500 square feet or part.