Job guide / tile setter, plumber
What a tiled shower costs to build properly
In a tiled shower the tile is the visible part and the waterproofing is the expensive part. Labor depends on the pan, the substrate, the tile size and how many niches, benches and corners there are. Tile setters earn a national median of $26.77 an hour. Permit lines exist for the pan itself: Portland charges $63.00 per fixture and San Francisco's single-unit category, which names shower pan installation, is $290.
A shower is a tank that drains
Tile and grout are not waterproof. Water gets behind them every day, and the layers underneath have to send it to the drain. Everything a competent tile setter does before the first tile goes up is about that: a sloped pan, a membrane that is continuous from the drain flange up the walls, sealed corners and penetrations, and a flood test with the drain plugged to prove it holds.
When you compare bids, compare this part first. Ask what waterproofing system each setter uses and whether they flood test. A bid that cannot answer is the expensive one, whatever its total says.
Where the days go
Demolition and substrate. Taking out an old tub or shower, fixing what the leak did to the framing, and installing backer board.
The pan. Site-built mortar beds take skill and drying time. Preformed pans are faster and limit the size and drain position.
Plumbing. Moving the drain or the valve is plumber's work, with its own permit line. Keeping both where they are is the single biggest saving available.
Layout and setting. Small mosaics conform to slopes but mean many grout joints. Large tiles need a very flat wall and careful handling. Patterns, borders and mitered edges are slow. Each niche is a small box with five waterproofed faces and a lot of cuts.
Waiting. Mortar, membrane, thinset and grout all cure. A shower cannot be compressed into consecutive hours, so the setter's trips are part of the price.
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $21.73 | $31.26 | $36.97 | $44.59 | $357 |
| Median | $26.77 | $38.51 | $45.55 | $54.93 | $439 |
| 75th percentile | $33.76 | $48.56 | $57.44 | $69.27 | $554 |
See tile setter wages for every metro.
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $24.13 | $34.71 | $41.06 | $49.51 | $396 |
| Median | $30.67 | $44.12 | $52.18 | $62.93 | $503 |
| 75th percentile | $40.92 | $58.86 | $69.62 | $83.97 | $672 |
See plumber wages for every metro.
Permit lines
| City | Line on the schedule | Fee | Schedule |
|---|---|---|---|
| Portland, OR | Water closet, tub/shower/shower pan, sink or lavatory, each | $63.00 | Plumbing Permit Fee Schedule, effective July 10, 2026 |
| San Francisco, CA | Category 1P, single residential unit: water service, sewer replacement, single plumbing fixture, shower pan, or a single kitchen or bathroom remodel (maximum two inspections) | $290 | Table 1A-C, Plumbing/Mechanical Issuance and Inspection Fees, effective July 12, 2026 |
| Grand Rapids, MI | Plumbing permit application, includes 1 inspection | $52.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
| Grand Rapids, MI | Plumbing: water closet, lavatory or bath tub-shower, each | $5.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
If the valve and drain stay put and no plumbing is altered, some cities will not require a permit for retiling. Once the pan or the piping changes, the lines above apply. Ask your building department, not the bidder.
Fixtures
| Series | BLS series ID | Month | Index | 12 months | Since Jan 2020 |
|---|---|---|---|---|---|
| Plumbing fixtures and fittings | WPU105 | October 2026 (p) | 381.1 | +6.0% | +33.9% |
| CPI-U, all items, U.S. city average | CUUR0000SA0 | September 2026 | 336.9 | +3.7% | +30.6% |
BLS does publish a producer price index for clay tile, but the readings we retrieved did not change across recent months, so we have not used it.
Comparing bids
Have each bidder state the waterproofing method, pan type, tile sizes they priced, number of niches, who supplies tile and setting materials, who does the plumbing, and whether glass is included. Tile supplied by the owner is fine, but it moves the risk of shortage and breakage to you.
Why is the labor higher for small tile than large?
More pieces, more joints to grout. Large tile has its own cost, though: walls must be flatter and each piece takes more care to set without lippage. The cheapest to set is a mid-size tile in a plain grid.
Does a shower rebuild need a permit?
Portland and San Francisco both list shower pans by name on their plumbing schedules, at $63.00 per fixture and $290 for the single-unit category. That is a strong hint that altering the pan is permitted work in those cities.
Related guides
- Bathroom remodel
- Gas line installation
- Heat pump water heater installation
- Lawn sprinkler system installation
- Sewer line replacement
- Water heater replacement
Sources
- BLS Occupational Employment and Wage Statistics, May 2025 metropolitan, state and national files
- BLS Employer Costs for Employee Compensation, June 2026, Table 4 (private industry by occupational and industry group)
- NAHB Eye on Housing, Remodelers Saw Profit Margin Gains in 2024 (Remodelers' Cost of Doing Business Study)
- Aswath Damodaran, NYU Stern, Margins by Sector (US), data as of January 2026
- BLS Producer Price Index commodity data and CPI-U, retrieved through the BLS public data API
- Portland, OR: Plumbing Permit Fee Schedule, effective July 10, 2026
- San Francisco, CA: Table 1A-C, Plumbing/Mechanical Issuance and Inspection Fees, effective July 12, 2026
- Grand Rapids, MI: Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026